Foressa Mountain Town Construction Updates Q4 2023

Phase Light 1A land development is fully completed, while Phase Light 1A site development is 93% complete, with a target completion in Q1 2025.

Phase Light 1B land development is 99% complete, with a target completion in Q1 2024, while Phase Light 1B site development is 77% complete, with a target completion in Q2 2025.

 

Amenities

The Main Pavilion is at 98% POC and substantially complete, poised to be operationally ready by Q2 2024.

The ongoing Phase Light 1A Streetscape is targeted to be completed by Q1 2024.

The Main Entry Signage is expected to reach completion by Q1 2024.

Phase Light 1A Pocket Parks and Outdoor Events Area are targeted for completion in Q3 2024.

 

Turnover

90 lots have been turned over to vecinos in Phase Light 1A.

 

Value Appreciation

Residential lot investments at Foressa Mountain Town are enjoying 92% value appreciation.

Priced at Php 7,300 per sqm during its launch year in 2017, a residential lot in this community is now at Php 14,000 per sqm.

 

Sales

The available inventory consists of 9 units in Phase Light 1A and 29 units in Phase Light 1B.

Know someone who is looking for a mountain sanctuary? Be one of our Referral Partners and earn up to Php 50,000* for every successful referral.

http://bit.ly/vecinoreferral

Reserve our special Hillside Lots now to get a P729K discount on regular terms and as much as P2.9M for cash payments.

Terms and conditions apply.